01 · Why IDR 10 Billion
A defined capital requirement across the complete development path.
The source investment case allocates IDR 10B across all phases from pre-construction through pre-opening for a proposed 13-suite hospitality asset.
IDR 10Bindicative development capital
13planned suites
~IDR 770Mindicative cost per suite
Hard construction65%
FF&E15%
Pre-development & legal5%
Pre-opening5%
Contingency5%
Other5%
- Budget remains subject to final design and bill of quantities
- Contractor pricing, permitting, and due diligence may change the requirement
- Indicative allocation—not a final construction budget